# Dask Delayed

Sometimes problems don’t fit into one of the collections like `dask.array` or
`dask.dataframe`. In these cases, users can parallelize custom algorithms
using the simpler `dask.delayed` interface. This allows you to create graphs
directly with a light annotation of normal python code:

```python
>>> x = dask.delayed(inc)(1)
>>> y = dask.delayed(inc)(2)
>>> z = dask.delayed(add)(x, y)
>>> z.compute()
5
>>> z.visualize()
```

![A Dask Delayed task graph with two "inc" functions combined using an "add" function resulting in an output node.](images/inc-add.svg)<iframe width="560"
        height="315"
        src="https://www.youtube.com/embed/SHqFmynRxVU"
        style="margin: 0 auto 20px auto; display: block;"
        frameborder="0"
        allow="accelerometer; autoplay; encrypted-media; gyroscope; picture-in-picture"
        allowfullscreen></iframe>

## Example

Visit [https://examples.dask.org/delayed.html](https://examples.dask.org/delayed.html) to see and run examples using Dask
Delayed.

Sometimes we face problems that are parallelizable, but don’t fit into high-level
abstractions like Dask Array or Dask DataFrame.  Consider the following example:

```python
def inc(x):
    return x + 1

def double(x):
    return x * 2

def add(x, y):
    return x + y

data = [1, 2, 3, 4, 5]

output = []
for x in data:
    a = inc(x)
    b = double(x)
    c = add(a, b)
    output.append(c)

total = sum(output)
```

There is clearly parallelism in this problem (many of the `inc`,
`double`, and `add` functions can be evaluated independently), but it’s not
clear how to convert this to an array or DataFrame computation. As written,
this code runs sequentially in a single thread.  However, we see that a
lot of this could be executed in parallel.

The Dask `delayed` function decorates your functions so that they operate
*lazily*.  Rather than executing your function immediately, it will defer
execution, placing the function and its arguments into a task graph.

| [`delayed`](delayed-api.html.md#dask.delayed.delayed)([obj, name, pure, nout, traverse])   | Wraps a function or object to produce a `Delayed`.   |
|--------------------------------------------------------------------------------------------------------------------|------------------------------------------------------|

We slightly modify our code by wrapping functions in `delayed`.
This delays the execution of the function and generates a Dask graph instead:

```python
import dask

output = []
for x in data:
    a = dask.delayed(inc)(x)
    b = dask.delayed(double)(x)
    c = dask.delayed(add)(a, b)
    output.append(c)

total = dask.delayed(sum)(output)
```

We used the `dask.delayed` function to wrap the function calls that we want
to turn into tasks.  None of the `inc`, `double`, `add`, or `sum` calls
have happened yet. Instead, the object `total` is a `Delayed` result that
contains a task graph of the entire computation.  Looking at the graph we see
clear opportunities for parallel execution.  The [Dask schedulers](scheduling.html.md)
will exploit this parallelism, generally improving performance (although not in this
example, because these functions are already very small and fast.)

```python
total.visualize()  # see image to the right
```

![A task graph with many nodes for "inc" and "double" that combine with "add" nodes. The output of the "add" nodes finally aggregate with a "sum" node.](images/delayed-inc-double-add.svg)

We can now compute this lazy result to execute the graph in parallel:

```python
>>> total.compute()
45
```

## Decorator

It is also common to see the delayed function used as a decorator.  Here is a
reproduction of our original problem as a parallel code:

```python
import dask

@dask.delayed
def inc(x):
    return x + 1

@dask.delayed
def double(x):
    return x * 2

@dask.delayed
def add(x, y):
    return x + y

data = [1, 2, 3, 4, 5]

output = []
for x in data:
    a = inc(x)
    b = double(x)
    c = add(a, b)
    output.append(c)

total = dask.delayed(sum)(output)
```

## Real time

Sometimes you want to create and destroy work during execution, launch tasks
from other tasks, etc.  For this, see the [Futures](futures.html.md) interface.

## Best Practices

For a list of common problems and recommendations see
[Delayed Best Practices](delayed-best-practices.html.md).

## Indirect Dependencies

Sometimes you might find yourself wanting to add a dependency to a task that does
not take the result of that dependency as an input. For example when a task depends
on the side-effect of another task. In these cases you can use
`dask.graph_manipulation.bind`.

```python
import dask
from dask.graph_manipulation import bind

DATA = []

@dask.delayed
def inc(x):
    return x + 1

@dask.delayed
def add_data(x):
    DATA.append(x)

@dask.delayed
def sum_data(x):
    return sum(DATA) + x

a = inc(1)
b = add_data(a)
c = inc(3)
d = add_data(c)
e = inc(5)
f = bind(sum_data, [b, d])(e)
f.compute()
```

`sum_data` will operate on DATA only after both the expected items have
been appended to it. `bind` can also be used along with direct dependencies
passed through the function arguments.

## Execution

By default, Dask Delayed uses the threaded scheduler in order to avoid data
transfer costs.
You should consider using [multi-processing](https://docs.dask.org/en/stable/scheduling.html#local-processes) scheduler or [dask.distributed](https://distributed.dask.org/en/latest/) scheduler
on a local machine or on a cluster if your code does not [release the GIL well](https://docs.dask.org/en/stable/graphs.html#avoid-holding-the-gil)
(computations that are dominated by pure Python code, or computations wrapping external
code and holding onto it).